Industrial · Go Dau

Phuoc Dong IP Textile Plant

A 25,000 m² textile plant in Phuoc Dong IP running 3 continuous shifts — demanding absolutely stable power and factory ventilation meeting workplace…

Phuoc Dong IP Textile Plant
InvestorCông ty CP Dệt may Phước Đông
LocationPhuoc Dong IP, Go Dau
Scale25,000 m² plant running 3 continuous shifts
Scope of workFull M&E package
RegionGo Dau
Timeline02/2022 – 10/2023

A 25,000 m² textile plant in Phuoc Dong IP running 3 continuous shifts — demanding absolutely stable power and factory ventilation meeting workplace temperature standards.

KT M&E delivered the full package: substation, power distribution, factory ventilation & cooling, process water systems. Handed over on the 18-month contractual milestone.